This is a high-level plan of action on establishing a complete work environment from scratch on Atlassian ecosystem of tools.
1. Bringing everything into one place
Client - process driver; Consultant - support with setting up whiteboard
Time estimate - defined by client
The initial phase is all about establishing the ground. It is recommended to use Whiteboards app to bring together all available materials in a free form, e.g. upload documents/reports, embed competitor’s / partners / customers' website pages, etc.
Use stickers to represent thoughts, decisions and requirements. Align the ideation stickers on a high-level timeline, classify across swim lanes, and outline dependencies.
2. Defining Jira Parameters
Client and Consultant work together with the Whiteboard
Time for collaborative work - 1 to 4 hours, depending on complexity
Guiding Considerations
3. Setting up Jira Instance according to the defined parameters
Set up by Consultant → Reviewed by Client → Feedback from Client → updates by Consultant.
Setup time may take from 2 hours (with out-of-box templates) to 24 hours (significant customization)
4. Transferring Work from Whiteboard to Projects Issues
Client and Consultant work together with the Whiteboard
Time for collaborative work - 1 to 4 hours, depending on complexity
Once the Jira projects are configured, stakeholders can convert all stickers into issues of the appropriate type and within the relevant project.